Before applying power, I check supply voltage at the device end, polarity, protective earth or functional ground, connector seating and network addressing. What else should be included so the first commissioning session produces a useful baseline?
A practical first-power-up checklist for a new LiDAR installation
◉ 35 · ◇ 2
2 ответов
Photograph the wiring and mounting position, record the device identification, and save the initial configuration before changing parameters. A short raw-data capture with the area empty is also valuable for later troubleshooting.
Confirm that the power supply remains within its required range during startup, not only with the sensor disconnected. Then verify link speed, packet loss and time settings before testing application logic.